A civic accountability organisation, Tracka, has questioned the reported expenditure of N621 million on six school projects at C&S Zion Primary School, Ilutitun, in Okitipupa Local Government Area of Ondo State, following its discovery that none of the projects has been delivered.
Tracka, in a Facebook post on Sunday, said Ondo State’s 2025 fourth-quarter Budget Implementation Report indicated that N621,032,539.29 had been spent on six interventions at the school, representing 96.63 per cent budget performance.
The projects include the renovation of classroom blocks, construction of additional classrooms and an Early Childhood Care, Development and Education (ECCDE) building, provision of teachers’ and ECCDE furniture, construction of a borehole, agricultural education facilities and sports equipment.
According to the organisation, N157.5 million was recorded for the renovation of two, three and six-classroom buildings, while N223.4 million was allocated to the construction of classroom blocks, an ECCDE building and two-bay toilets.
It said another N123.5 million was recorded for the supply of 100 teachers’ and ECCDE furniture, N46.4 million for water supply and sanitation, N32.7 million for agricultural education and N37.3 million for sports equipment.

Tracka observed that the proposed budget for the six interventions, initially put at N445.1 million, was inflated to N642.6 million in the approved budget, representing a 44.3 per cent increase.
The organisation said a monitoring visit to the school in November 2026 revealed that the projects captured in the budget implementation report had allegedly not been delivered.
It said the only classroom block in use had visible cracks and detached roofing sheets, while another classroom block had been abandoned and overgrown with weeds.
According to Tracka, the school also confirmed that it had not received any of the items listed under the six interventions.

The organisation questioned how the state government could report 96.63 per cent budget performance for the projects despite the alleged absence of corresponding deliverables at the school.
“How can N621m be reported as disbursed when none of the budgeted interventions have been delivered? Who received the money? Where is the evidence of implementation?” Tracka asked.
Tracka disclosed that it had submitted a Freedom of Information (FOI) request to the Ondo State Universal Basic Education Board (SUBEB), seeking details of the contractors, specific project locations and implementation status of the projects.
A copy of the letter, dated June 12, 2026, and addressed to the Permanent Secretary of Ondo SUBEB, showed that the organisation requested the information under the Freedom of Information Act, 2011.
The organisation, however, said it had yet to receive a response to the request.
Tracka called on the Ondo State Government and SUBEB to explain the reported expenditure, while urging the Economic and Financial Crimes Commission (EFCC) and the Independent Corrupt Practices and Other Related Offences Commission (ICPC) to investigate the disbursements and establish how the funds were utilised.
It said the alleged non-delivery of the projects raised concerns about the management of public funds and the quality of education available to pupils at the school.